AERB Clears RAPP-8 at Rawatbhata for First Criticality

The regulator has permitted the 700 MWe Rajasthan reactor to start its first controlled chain reaction. Grid power is still some way off.

N
By News Desk
Jaipur · Published: · Updated:
हिंदी में पढ़ें

India's nuclear regulator has approved the First Approach to Criticality of Unit-8 at the Rajasthan Atomic Power Project, reportedly on 19 November 2026. Further tests and approvals are needed before it supplies electricity.

AERB Clears RAPP-8 at Rawatbhata for First Criticality
AERB Clears RAPP-8 at Rawatbhata for First Criticality Photo: Anine News
Share

Quick answer: India's nuclear regulator, the Atomic Energy Regulatory Board (AERB), has permitted the First Approach to Criticality (FAC) of Unit-8 of the Rajasthan Atomic Power Project (RAPP-8) at Rawatbhata. Reports say the clearance came on 19 November 2026. The 700 MWe reactor is not yet supplying electricity; several commissioning steps and further approvals remain.

ReactorRAPP Unit-8, Rawatbhata, Chittorgarh district, Rajasthan
Type and size700 MWe indigenous Pressurised Heavy Water Reactor (PHWR)
ApprovalAERB permission for First Approach to Criticality, reported 19 November 2026
Earlier stepInitial fuel loading began in September 2026
StatusNot yet generating power or connected to the grid

What has the AERB approved for RAPP-8?

The regulator has cleared the reactor for its first approach to criticality, the stage at which a controlled, self-sustaining nuclear chain reaction is started for the first time, initially at a very low power level. Reports citing the clearance say it followed a regulatory review of the reactor's design, construction quality, commissioning test results and operational preparedness.

The AERB has said it will keep close oversight of the remaining commissioning programme through safety reviews, inspections and continuous monitoring by its resident site observers.

Does this mean RAPP-8 is producing electricity?

No. Criticality is a commissioning milestone, not the start of power supply. After it, the unit has to complete low-power physics experiments and other prescribed tests, obtain further regulatory permissions, and only then be synchronised with the grid and move to commercial operation.

In September 2026, the Nuclear Power Corporation of India Limited (NPCIL) began initial fuel loading at the unit after receiving AERB permission, and said commercial operation was targeted within the current financial year.

How does this compare with RAPP-7?

RAPP-8 is the second of two 700 MWe reactors built as a pair at Rawatbhata. Its sister unit, RAPP-7, reached criticality on 19 September 2024 and was connected to the grid in March 2025, according to published reports. RAPP-8 is described as India's fourth indigenous 700 MWe PHWR, following Kakrapar units 3 and 4 in Gujarat and RAPP-7.

Why does it matter for India's nuclear capacity?

Once operational, RAPP-8 will add 700 MWe at a site that already hosts several units. The 700 MWe PHWR is the standard design for India's current fleet-mode nuclear expansion, so each unit that clears commissioning is closely watched as a test of the programme's pace.

Frequently asked questions

What is first approach to criticality?

It is the point at which a reactor's fuel first sustains a controlled chain reaction, run at very low power to verify behaviour before power is raised.

Where is RAPP-8 located?

At Rawatbhata in Rajasthan's Chittorgarh district, alongside the other units of the Rajasthan Atomic Power Station.

Who operates the plant?

NPCIL, which builds and operates India's civil nuclear power plants, while the AERB acts as the independent regulator.

When will RAPP-8 supply power to the grid?

No official date for grid connection has been given in the reports reviewed. NPCIL had earlier said it was targeting commercial operation in the current financial year.

Is the reactor already running at full power?

No. Power is raised in stages after criticality, subject to tests and regulatory approvals.

Details are based on the AERB clearance as reported on 19-20 November 2026 and NPCIL's September 2026 fuel-loading announcement; the official release could not be opened independently at the time of writing.