HAL Reportedly Assures IAF First Tejas Mk-1A Batch by March 2027

Reports say 16 to 18 jets are promised, years after the original delivery date was missed.

N
By News Desk
New Delhi · Published: · Updated:
हिंदी में पढ़ें

HAL has reportedly told the Indian Air Force it will deliver its first Tejas Mk-1A jets by 31 March 2027. IAF chief Ashutosh Dixit has said the first squadron will be formed within this financial year.

HAL Reportedly Assures IAF First Tejas Mk-1A Batch by March 2027
HAL Reportedly Assures IAF First Tejas Mk-1A Batch by March 2027 Photo: Anine News
Share

Quick answer: HAL has reportedly assured the Indian Air Force that it will hand over its first batch of Tejas Mk-1A fighters by 31 March 2027, with some reports putting the number at 16 to 18 jets. The timeline has slipped repeatedly, but Air Chief Marshal Ashutosh Dixit said on 16 November that the first squadron should be formed within the current financial year at the latest.

AircraftHAL Tejas Mk-1A light combat aircraft
Latest targetFirst squadron by end of March 2027
Reported quantity16 to 18 jets (a squadron is typically about 18)
Original start of deliveriesEarly 2024 (missed)
Total Mk-1A orders180 jets (83 plus 97)
IAF fighter squadrons29 against a sanctioned 42

What has HAL promised the Air Force?

Reports published on 24 November say Hindustan Aeronautics Limited has committed to delivering between 16 and 18 Tejas Mk-1A aircraft by 31 March 2027, after a meeting of senior IAF and HAL officials earlier in the month. That figure comes from officials familiar with the discussions rather than from an on-record HAL statement, so it should be treated as reported rather than formally confirmed.

The same reports say the IAF has agreed to accept a full squadron by the deadline, but will not dilute technical specifications or operational capability just to speed up handovers.

What did the IAF chief say?

Speaking at the ANI National Security Summit in New Delhi on 16 November, Air Chief Marshal Ashutosh Dixit said the Air Force expects to form its first Mk-1A squadron by the end of March 2027 at the latest. He said the jets would begin joining "very shortly". He also indicated that the heavier Tejas Mk-2 could follow "maybe next year" and that work on the stealth AMCA programme is progressing.

Why have the deliveries been delayed?

HAL missed the schedule that would have started handovers in early 2024. The main cause has been the late arrival of F404-IN20 engines from US firm GE Aerospace, along with the complexity of integrating the AESA radar, missiles and other systems. HAL said in September 2026 that it had received 10 of these engines and completed 27 airframes, according to the reports.

Officials quoted in the reports say most hardware problems, including weapons-testing issues, are resolved, and that radar and software fixes are close to completion. HAL still has to finish documentation and obtain clearances from the certification and quality-assurance agencies before handover.

How serious is the IAF's squadron shortage?

The Air Force currently operates about 29 fighter squadrons against a sanctioned strength of 42, which defence reports describe as its lowest level in about six decades. The retirement of the MiG-21 fleet in September 2025 added to the gap. The Mk-1A, a 4.5-generation fighter with an AESA radar, beyond-visual-range missiles and an electronic warfare suite, is meant to help fill it.

The IAF has ordered 180 Mk-1A jets in total: 83 under a contract signed in February 2021 and 97 under a second order in September 2025. Reports differ on the rupee value of the first contract, so it is not stated here.

Frequently asked questions

When will the first Tejas Mk-1A reach the IAF?

The IAF chief says the first squadron will be formed by the end of March 2027 at the latest. An earlier report suggested one or two jets might be handed over as early as January 2027.

How many jets is HAL expected to deliver?

Reports based on officials say 16 to 18 aircraft by 31 March 2027. HAL has not issued a public statement confirming the number.

Why is the Mk-1A late?

Mainly because of delayed GE F404 engines and the difficulty of integrating radar and weapons, according to defence reporting.

How many Mk-1A jets has India ordered?

A total of 180: 83 from the 2021 contract and 97 from the September 2025 order.

What is the IAF's current squadron strength?

About 29 fighter squadrons, compared with the sanctioned 42.

Details are drawn from Air Chief Marshal Dixit's remarks at the ANI National Security Summit and from reports on HAL's commitment; the 16-18 jet figure is attributed to unnamed officials.